Significant marsh loss has occurred south of Lake Hermitage with the construction of numerous oil and gas canals, subsidence, and sediment deprivation. The most significant loss occurred during the 1960s and 1970s. Based on the hyper-temporal analysis conducted by USGS for the extended boundary, loss rates in the project area are estimated to be -1.16% per ear for the period 1984 to 2011.
The goals of the Bayou Grande Cheniere Marsh and Ridge Restoration Project (BA-173) are to restore marsh habitat adjacent to the eastern shoreline of Bayou Grande Cheniere, reestablish the corresponding section of the bayou’s forested ridge habitat along this shoreline, and create terraces to restore marsh in open water habitat. Specific objectives are to 1) restore 302 acres of brackish marsh habitat, 2) construct the marsh platform to an elevation that supports healthy marsh; 3) reestablish 10,625 linear feet of the historic Bayou Grande Cheniere Ridge to an elevation that supports healthy woody vegetation, 4) establish the ridge with diverse native woody species, and 5) construct 12,000 linear feet of terraces to an elevation that will support healthy marsh.
Riverine sediments will be hydraulically dredged and pumped via pipeline to create/nourish approximately 302 acres of marsh. Containment dikes will be constructed around the perimeter of the marsh creation cells. The proposed design is to place the dredged material to a target fill elevation of +3.0 feet which would ultimately settle to an approximate elevation of just under +0.75 feet NAVD88 (Geoid 12A) at TY20. Tidal creeks are expected to form naturally and containment dikes will be gapped and degraded to enhance the naturally formed tidal creeks.
Hydraulically dredged river sediments will be used to restore 10,625 linear feet of the Bayou Grande Cheniere Ridge. The ridge will have 25-ft crown width, a target height of +4.5 ft NAVD88, and side slopes of 1(V):8(H). Herbaceous plantings (e.g., seashore paspalum) will be necessary immediately after construction and bottomland hardwood species (seedlings and saplings) will be planted by Year 3. Funding for tallow control and maintenance plantings is also included.
In addition, 11,700 linear feet of earthen terraces will be constructed resulting in the creation of approximately 10 acres of wetlands benefiting 154 acres of open water. Each terrace segment will be approximately 450 feet long and built to an elevation of +3.0 feet, with a 25-foot crown width and 1(V):4(H) side slopes. The terraces will be constructed with a bucket dredge using in situ material from within the terrace field.
This project is located in Plaquemines Parish west of the Mississippi River near West Pointe a la Hache. Specifically, the project features are south of Lake Hermitage and along the eastern side of Bayou Grande Cheniere.
This project is on Priority Project List (PPL) 23.
The Bayou Grande Cheniere Marsh & Ridge Restoration project sponsors include:
- Federal Sponsor: U.S. Fish and Wildlife Service
- Local Sponsor: Coastal Protection and Restoration Authority
Keep up with this project and other CWPPRA projects on the project page.