The Terrebonne Basin is an abandoned delta complex, characterized by a thick section of unconsolidated sediments that are undergoing dewatering and compaction, contributing to high subsidence, and a network of old distributary ridges extending southward from Houma. Historically, subsidence and numerous oil and gas canals and pipelines in the area have contributed significantly to wetland losses. Since 1932, the Terrebonne Basin has lost approximately 20% of its wetlands. Current loss rates range from approximately 4,500 to 6,500 acres/year. This loss amounts to about130,000 acres over the next 20 years. One-third of the Terrebonne Basin’s remaining wetlands would be lost to open water by the year 2040. The wetland loss rate in the area is -0.79%/year based on USGS data from 1984 to 2016.

The proposed project’s primary feature is to create and/
or nourish approximately 504 acres of intermediate marsh adjacent to Lake De Cade and restore 11,726 linear feet of ridge habitat along the northern bank of Bayou De Cade. To achieve this, sediment will be hydraulically pumped from a borrow source in Lake De Cade. The borrow area in Lake De Cade would be located and designed in a manner to avoid and minimize environmental impacts (e.g., to submerged aquatic vegetation and water quality) to the maximum extent practicable. Containment dikes will be constructed around the marsh creation area to retain sediment during pumping. No later than three years post construction, the containment dikes will be degraded and/or gapped. Additionally, the newly constructed marsh will be planted after construction to stabilize the platform and reduce time for full vegetation. It is anticipated that material for the ridge feature will be mechanically dredged from adjacent areas within Bayou De Cade and/or the marsh area and lifted to a crown elevation of +5.0 feet, 25 feet wide, and will be planted.

map

This project is located in Region 3, Terrebonne Basin, Terrebonne Parish, Lake Mechant Mapping Unit.

This project was approved for Phase I Engineering and Design in January 2017 and is on Priority Project List (PPL) 26.

The Bayou Decade Ridge and Marsh Creation project sponsors include:

Keep up with this project and other CWPPRA projects on the project page.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s