Bayou Dupont Ridge Creation and Marsh Restoration (BA-48)

BE.48_banner

Problems: There is widespread historic and continued rapid land loss within the project site and surrounding areas resulting from subsidence, wind erosion, storms, and altered hydrology. Land loss data provided by the U.S. Geological Survey indicates that loss was occurring at a rate of 1.7% per year prior to construction. The natural limits of Bayou Dupont were difficult to determine in some areas because land loss was causing a merge of the bayou to adjacent water bodies. Natural tidal flow and drainage of patterns that once existed through the bayou were circumvented by the increasing area of open water.

Restoration Strategy: Project goals included: 1) creating and nourishing approximately 390 acres of marsh through sediment pipeline delivery from the Mississippi River; and   2) creating over two miles of ridge (10.5 acres of ridge habitat) along a portion of the southwestern shoreline of Bayou Dupont. Sediment from the river was hydraulically pumped to the project site to construct both the marsh and ridge features and additional material was dredged from Bayou Dupont to cover the ridge. The ridge is designed to mimic the configuration of other natural ridges within the watershed, and includes a constructed elevation conducive for the growth of native vegetation such as live oak, hackberry, and yaupon. The ridge is helping to redefine the limits of Bayou Dupont and reestablish the natural bank that once flanked the bayou and  protected adjacent marshes.

BA.48_map

Location: This project is located within the Barataria Basin in Jefferson and Plaquemines Parishes. The marsh creation area is located along Bayou Dupont southeast of the waterbody known as the Pen.

Progress to Date: Construction began in the Fall of 2014 in conjunction with the Mississippi River Long Distance Sediment Pipeline Project (BA-43EB) and Bayou Dupont Sediment Delivery-Marsh Creation #3 (BA-164). Construction of the Bayou Dupont (BA-48) portion was completed in fall of 2015.

This project is on Priority Project List 17.

Hydrologic Restoration and Vegetative Planting (BA-34-2)

34.2_banner_final.png

Problems:
The Lac des Allemands River Basin Initiative identified the following specific problems within the Lac des Allemands Watershed: drainage impairments; water quality impairments; loss of marsh; and decline of cypress forest. Many years of study by Louisiana State University researchers in these swamps have demonstrated that, because of impoundment, subsidence, and inadequate accretion of sediments and organic matter, some areas are already highly stressed and converting to open water, floating aquatic plants, and fresh marsh. Also, the Coast 2050 report suggests that other areas of the swamps throughout the basin will likely convert to open water or floating marsh by the year 2050. These problems are caused by the loss of river water along with the associated sediment and nutrients necessary for swamp health. The loss of river water can be attributed to the leveeing of the Mississippi River. Impoundment caused by roads, drainage canals, and spoil banks is also a major cause of degradation of these swamps.
Restoration Strategy:

The original proposed restoration strategy included installing two small siphons (averaging 400 cubic feet per second) to divert water from the Mississippi River; gapping spoil banks on Bayou Chevreuil; gapping spoil banks along the borrow beside Louisiana Highway 20; installing culverts under Louisiana Highway 20; improving drainage in impounded swamps; and planting cypress and tupelo seedlings in highly degraded swamp areas.

The proposed diversion from the Mississippi River was to bring fresh water, fine-grained sediments, and nutrients into the upper des Allemands swamps, which would have helped maintain swamp elevation, improve swamp water quality, and increase productivity and regrowth of young trees as older trees die. However, after hydrologic modeling and more detailed engineering/design and cost estimation, it was determined that the siphon would cost far more than originally anticipated. For that reason, the CWPPRA Task Force approved the project sponsors’ request to re-scope the project to eliminate the siphon feature, and to focus on the remaining project features.

ba.34.2_map.png

Location: The project is located West of Lac des Allemands in St. James Parish, Louisiana, south of the town of South Vacherie, bordered on the south by Bayou Chevreuil, and on the east by LA Highway 20.

Progress to Date: The Louisiana Coastal Wetlands Conservation and Restoration Task Force approved Phase 1 funding in January 2001. In June 2013, the Task Force approved a request to change the scope of the project to eliminate a siphon feature and focus on the remaining original hydrologic restoration and vegetative planting project features. The Louisiana Coastal Protection and Restoration Authority performed the engineering and design services. Design was completed in October 2015 and Phase 2 funds for construction was approved by the Task Force in January 2016. Construction activities for excavation and placement began in October 2017 and ended on December 20, 2017, vegetative plantings occurred in late January, and officially completed on February 2, 2018.

The three (3) principal project features included:

1. Eight (8), 400-foot-long, strategically designed gaps were cut in the northern Bayou Chevreuil spoil bank to reverse the effects of impoundment;

2. Sixteen (16) spoil placement areas were created on each side of the channel banks; (1 placement area on both sides of each gap) to beneficially use the dredged material on site;

3. Seven hundred (700) Bald Cypress and one hundred (100) Water Tupelo saplings were planted in the constructed spoil placement areas to start swamp regeneration and swamp productivity.

This project enhanced 2,395 acres of swamp habitat that would have continued to degrade without the project.

This project is on Priority Project List (PPL) 10.

The sponsors include:

Federal Sponsor: U.S. Environmental Protection Agency

Local Sponsor: Coastal Protection and Restoration Authority (CPRA)

 

 

Pass Chaland to Grand Bayou Pass Barrier Shoreline Restoration (BA-35)

Above image from lacoast.gov

Reasons for Restoration:

Prior to construction, wetlands, dune, and swale habitats within the project area had undergone substantial loss due to subsidence, absolute sea-level rise, and marine- and wind induced shoreline erosion. In addition, oil and gas activities, such as pipeline construction, also contributed to the loss.

Marine processes acting on the abandoned deltaic headlands rework and redistribute previously deposited sediment. Fragmentary islands develop due to breaches in the barrier headland. Subsequently, increased tidal prism storage (the total volume of salt water that moves in and out of a bay with the tide) and storm-related impacts have led to inlet and pass formation across the newly formed islands. The Bay Joe Wise beach rim was receded and decreased to a critical width that was susceptible to breaching.

Land area in the project area had decreased from 1932 to 2000. Storms occur approximately every 8.3 years along the Barataria shoreline. Because approximately 100 feet of shoreline is eroded with each storm, shorelines of 100 feet or less are considered in imminent danger of breaching.

Restoration Strategies:

The project’s objectives were: 1) preventing the breaching of the Bay Joe Wise shoreline by increasing barrier shoreline width; 2) increasing back-barrier, emergent marsh area by some 226 acres to maintain the barrier shoreline; and 3) creating emergent marsh suitable for tidal aquatic habitats.

The Project features included a constructed beach and dune platform along approximately 2.7 miles of the gulf shoreline. Constructed landward of the beach and dune was a marsh platform with an average width of 860 feet spanning the entire project length. A water exchange channel was incorporated on the western end of the Project to facilitate flushing of Bay Joe Wise through Pass Chaland. The Project created over 420 acres requiring 2.95 million cubic yards of fill dredged from ebb shoal borrow areas. Other project features included installation of sand fencing concurrent with dune construction, dune and marsh vegetative plantings, and post-construction gapping of retention dikes.

FP_BA-35_Banner map.png Above image from lacoast.gov

Location:

The project is located in the Barataria Basin, between Pass Chaland and Grand Bayou Pass in Plaquemines Parish, Louisiana.

This project is on Priority Project List (PPL) 11.

 

Source: 

Louisiana Coastal Wetlands Conservation and Restoration Task Force “Pass Chaland to Grand Bayou Pass Barrier Shoreline Restoration (BA-35)”. 2 March 2018, https://www.lacoast.gov/reports/gpfs/BA-35.pdf.