Holly Beach Sand Management (CS-31)

wordpress fact sheet banner CS-31-01

The Chenier Plain shoreline was created with sediment transported by the Mississippi River’s periodic westward oscillation. The swales that characterize the Chenier Plain were created by the deposition of these alluvial sediments, and these same sediments also served to extend the shoreline gulfward and create the area’s expansive mudflats.

Chronic erosion in this area is caused by a lack of sand and sediment caused by the channelization and regulation of the Mississippi and Atchafalaya rivers to the east. In addition, the Calcasieu and Mermentau rivers are not supplying coarse-grained sediment to the area, and the Cameron Jetties associated with the Calcasieu Ship Channel deflect the little material that does exist away from the project area.

The project’s goals are: (1) to protect approximately 8,000 acres of existing, low energy intermediate and brackish marsh wetlands north of the forested ridge and (2) to create and protect roughly 300 acres of beach dune and coastal chenier habitat from erosion and degradation.

The project also provides protection for the wooded chenier to the west, which has been purchased by the Baton Rouge Audubon Society. It is being maintained as a sanctuary because of its importance as habitat for Neotropical migratory birds.

The project plan consists of placing approximately 1.7 million cubic yards of high quality sand on the beach to reestablish a more historical shoreline, as well as improve the effectiveness of the existing segmented breakwater system.

map

The project is located west of Calcasieu Pass along the Gulf of Mexico shoreline, extending between Holly Beach and Constance Beach in Cameron Parish, Louisiana.

This project was selected for Phase 2 (construction) funding at the August 2001 Louisiana Coastal Wetlands Conservation and Restoration Task Force meeting. Since that time, 1.75 million cubic yards of sand were added to the beach. Sand placement was completed in March 2003.

Project staff installed 102,000 linear feet of vegetative plantings at dune elevation on the Holly Beach dredge platform; 20,400 four-inch containers of bitter panicgrass (Panicum amarum) were planted. The installation of the plantings was completed in August 2003. Cameron Parish believes this project is what saved HWY 82 from being washed out during Hurricane Rita.

This project is on Priority Project List 11.

The Federal Sponsor is NRCS

The local sponsor is CPRA

Black Bayou Hydrologic Restoration (CS-27)

wordpress fact sheet banner CS-27-01-01

The purposes of the Black Bayou Hydrologic Restoration
project are to (1) restore coastal marsh habitat, and (2) slow
the conversion of wetlands to shallow, open water in the
project area. The project limits the amount of saltwater
intrusion into the surrounding marsh and canals from the
GIWW and reduces erosion caused by wave action from
nearby boats and tides.

A 22,600-foot rock dike was placed on the southern spoil
bank of the GIWW. A barge bay weir (70-foot bottom
width) was constructed in Black Bayou Cutoff Canal. Weirs
with boat bays (10-foot bottom widths) were constructed in
Burton Canal and Block’s Creek. A collapsed weir was
plugged and replaced by a fixed crest steel sheet-pile weir
with a state-of-the-art, self-regulating tidegate. Spoil
material from weir installation and the dredging of access
routes was deposited in nearby open water areas to the
height of marsh elevations. The $3 million construction
contract included installation of 55,000 marsh plants over the
next two planting seasons.

map.jpg

This project, sponsored by the National Marine Fisheries
Service and the Louisiana Department of Natural Resources,
is a 25,529 acre wetland located in Cameron and Calcasieu
Parishes, Louisiana. Bordered by the Gulf Intracoastal
Waterway (GIWW), Sabine Lake, Black Bayou, and Gum
Cove Ridge, the project area consists of tidally-influenced
intermediate and brackish marshes.

Construction is completed. Installation of vegetative
plantings were completed in April 2002. The monitoring
plan was finalized in March 2000, and monitoring has
begun.

This project is on Priority Project List 6.

Federal Sponsor: NOAA 

Local Sponsor: CPRA