Holly Beach Sand Management (CS-31)

wordpress fact sheet banner CS-31-01

The Chenier Plain shoreline was created with sediment transported by the Mississippi River’s periodic westward oscillation. The swales that characterize the Chenier Plain were created by the deposition of these alluvial sediments, and these same sediments also served to extend the shoreline gulfward and create the area’s expansive mudflats.

Chronic erosion in this area is caused by a lack of sand and sediment caused by the channelization and regulation of the Mississippi and Atchafalaya rivers to the east. In addition, the Calcasieu and Mermentau rivers are not supplying coarse-grained sediment to the area, and the Cameron Jetties associated with the Calcasieu Ship Channel deflect the little material that does exist away from the project area.

The project’s goals are: (1) to protect approximately 8,000 acres of existing, low energy intermediate and brackish marsh wetlands north of the forested ridge and (2) to create and protect roughly 300 acres of beach dune and coastal chenier habitat from erosion and degradation.

The project also provides protection for the wooded chenier to the west, which has been purchased by the Baton Rouge Audubon Society. It is being maintained as a sanctuary because of its importance as habitat for Neotropical migratory birds.

The project plan consists of placing approximately 1.7 million cubic yards of high quality sand on the beach to reestablish a more historical shoreline, as well as improve the effectiveness of the existing segmented breakwater system.

map

The project is located west of Calcasieu Pass along the Gulf of Mexico shoreline, extending between Holly Beach and Constance Beach in Cameron Parish, Louisiana.

This project was selected for Phase 2 (construction) funding at the August 2001 Louisiana Coastal Wetlands Conservation and Restoration Task Force meeting. Since that time, 1.75 million cubic yards of sand were added to the beach. Sand placement was completed in March 2003.

Project staff installed 102,000 linear feet of vegetative plantings at dune elevation on the Holly Beach dredge platform; 20,400 four-inch containers of bitter panicgrass (Panicum amarum) were planted. The installation of the plantings was completed in August 2003. Cameron Parish believes this project is what saved HWY 82 from being washed out during Hurricane Rita.

This project is on Priority Project List 11.

The Federal Sponsor is NRCS

The local sponsor is CPRA

Cameron Prairie National Wildlife Refuge Shoreline Protection (ME-09)

wordpress fact sheet banner ME-09-01

The management levee between the GIWW and the
Cameron Prairie National Wildlife Refuge was in danger
of breaching as a result of erosion from boat traffic in the
GIWW. If breaching had occurred, wave energy from the
GIWW and salt water would have entered the organic,
freshwater wetlands.

A 13,200-foot rock breakwater was constructed 50 feet
from the northern bank of the GIWW to prevent waves
caused by boat traffic from overtopping and eroding the
remaining spoil bank.
The project’s effectiveness is being evaluated by shoreline
movement surveys and by comparing pre-construction and
post-construction aerial photographs for changes in marsh
loss rates.

map.jpg

This project is located in Cameron Parish, Louisiana, on
the north shore of the Gulf Intracoastal Waterway
(GIWW), approximately 7 miles southeast of Sweet Lake
and to the east of Louisiana Highway 27 at its intersection
with the GIWW. It encompasses 640 acres of fresh marsh
and open water.

During 1993-97, while the project area had a 4.9% increase in
water coverage due to management for waterfowl, the
reference area remained unchanged.

The results of shoreline monitoring indicate that the project
has protected 13,200 feet of shoreline, along with 247 acres of
marsh north of the dike. This protection is expected to accrue
throughout the life of the project for a net restoration of at
least 23 acres. Monitoring has shown that the GIWW’s
northern shoreline advanced 9.8 feet per year in the project
area while retreating at a rate of 3.0 feet per year in the
reference area, indicating that low sediment availability does
not prohibit wetland creation behind rock dikes on navigation
channels.

To date, the project has exhibited success. It is expected that
the project area will continue to accrete new wetland area
between the spoil bank and the rock dike, further
safeguarding the adjacent wetland area from encroachment by
the GIWW.

This project is on Priority Project List 1.

 

The Federal Sponsor is USFWS

The Local Sponsor is CPRA

Whiskey Island Back Barrier Marsh Creation (TE-50)

wordpress fact sheet banner TE-50-01

Gulfside and bayside erosion has resulted in the narrowing of Whiskey Island (and the entire Isles Dernieres chain) as the two shorelines migrate toward each other, resulting in a 68 percent decrease in average width for the Isles Dernieres. Within 100 years, the entire subaerial portion of the Isles Dernieres barrier island system is expected to disappear except for small land fragments associated with the western end of Whiskey Island and the eastern end of East Island. However, some estimates project the Isles Dernieres will disappear much earlier. Other predictions suggest that, without restoration, Whiskey Island could become a subaqueous sand shoal by 2019. Another CWPPRA restoration project, Whiskey Island Restoration (TE-27), which included placement of dredge material, vegetative planting, and sand fencing, was completed in 2000.

The goal of the TE-50 project is to increase the longevity of the previously restored and natural portions of the island by increasing the island’s width. Increasing the island’s width will help to retain sand volume and elevation. Approximately 319 acres of back barrier intertidal marsh habitat, 5,865 linear feet of tidal creeks, three 1-acre tidal ponds and 13,000 linear feet of protective sand dune were created by semiconfined disposal and placement of dredged material. The sediment was dredged from a sediment source in the Gulf of Mexico near the island. The area was planted with native marsh vegetation to colonize and protect the newly-placed marsh soil.

map.jpg

Whiskey Island, one of five islands that make up the Isles Dernieres barrier island chain, is located 18 miles southwest of Cocodrie in Terrebonne Parish, Louisiana. The island is surrounded by Coupe Colin to the west, Whiskey Pass to the east, Lake Pelto, Caillou Boca, and Caillou Bay to the north, and the Gulf of Mexico to the south.

The CWPPRA Task Force approved funding for construction (phase 2) at the February 13, 2008 Task Force meeting. Construction began in March 2009 and initial construction was completed in November 2009.Vegetative plantings were installed at the project site in June of 2010 and October 2011.

This project is on Project Priority List 13.

Federal Sponsor: EPA

Local Sponsor: CPRA

East Sabine Lake Hydrologic Restoration (CS-32)

wordpress fact sheet banner CS-32-01

The lower salinity marshes are converting to shallow, open water due to elevated salinity events and subsidence. Navigation channels provide a direct route for salt water to infiltrate the marsh, disrupt the natural water circulation, and allow rapid runoff of fresh water. The larger Sabine-Neches Waterway and the Gulf Intracoastal Waterway (GIWW) have allowed saltwater intrusion into the project area’s fresh and intermediate marshes. Elevated tidal fluctuations in these channels have led to increased water flow, which has increased the conversion of marsh to open water. Area marsh loss is also caused by wave action along Sabine Lake and interior marsh shorelines and other natural causes (i.e., subsidence).

The project features include: a rock weir in Pines Ridge Bayou; three culverts with flap gates at Bridge Bayou; a 3,000 foot-long rock rip-rap breakwater along the Sabine Lake shoreline at Willow Bayou; a weir/plug at the opening at Starks South Canal Section 16 levee; and 232,000 linear feet of vegetated earthen terraces in the vicinity of Greens Lake.

map.jpg

The project is located in the western portion of the Sabine National Wildlife Refuge from Pool 3 to the eastern shoreline of Sabine Lake in Cameron Parish, Louisiana.

Construction was completed in October 2010.

This project is on Priority Project List 10.

The Federal Sponsor is U.S. Fish and Wildlife Service

The Local Sponsor is CPRA

South Lake Lery Shoreline & Marsh Restoration (BS-16)

wordpress fact sheet banner BS-16-01

Reasons for Restoration:

According to USGS-land loss analysis, much of the southern and western shorelines of Lake Lery and the surrounding wetlands were heavily damaged in 2005 by Hurricane Katrina. In the years following this storm, wind induced waves within the lake have begun to cause further damage to the lake’s shorelines. Currently the shorelines have become so damaged that the interior emergent marshes that are still intact are being exposed to the damaging waves. This has caused an increased loss of emergent marsh habitat. Even with the benefits of the Caernarvon Diversion Structure, without some type of restoration in this area, these marshes may not be able to fully recover.

Restoration Strategy:

This is a marsh creation and shoreline restoration project. The marsh creation aspect of the project will have a hydraulic dredge extract material from the Lake Lery water bottom and pump that material into contained marsh creation cells located south and west of the southern and western Lake Lery shorelines. This will create and/or nourish approximately 642 acres of intertidal intermediate marsh. The shoreline restoration component of the project will  have a barge-mounted dragline excavating material from the bottom of Lake Lery and placing that material along the southern and western shorelines. This restored shoreline will have a 50 foot crown width and be built to a height considered high intertidal marsh.

BS-16_map.png
Progress to Date:
This project received Phase II funding in January 2012. Construction began in the spring of 2015 and is expected to be complete in the summer of 2018. All marsh creation is complete. Earthwork and vegetative plantings associated with the lake rim embankments are complete. There are ongoing discussions regarding erosion concerns along lake rim embankments.
This Project is on Project Priority List 17.

The Sponsors for this Project include:

sponsors_1.pngFederal Sponsor: U.S. Fish and Wildlife Service

Local Sponsor: CPRA

 

Bayou Grande Cheniere Marsh & Ridge Restoration

banner

Significant marsh loss has occurred south of Lake Hermitage with the construction of numerous oil and gas canals, subsidence, and sediment deprivation. The most significant loss occurred during the 1960s and 1970s. Based on the hyper-temporal analysis conducted by USGS for the extended boundary, loss rates in the project area are estimated to be -1.16% per ear for the period 1984 to 2011.

The goals of the Bayou Grande Cheniere Marsh and Ridge Restoration Project (BA-173) are to restore marsh habitat adjacent to the eastern shoreline of Bayou Grande Cheniere, reestablish the corresponding section of the bayou’s forested ridge habitat along this shoreline, and create terraces to restore marsh in open water habitat. Specific objectives are to 1) restore 302 acres of brackish marsh habitat, 2) construct the marsh platform to an elevation that supports healthy marsh; 3) reestablish 10,625 linear feet of the historic Bayou Grande Cheniere Ridge to an elevation that supports healthy woody vegetation, 4) establish the ridge with diverse native woody species, and 5) construct 12,000 linear feet of terraces to an elevation that will support healthy marsh.

Riverine sediments will be hydraulically dredged and pumped via pipeline to create/nourish approximately 302 acres of marsh. Containment dikes will be constructed around the perimeter of the marsh creation cells. The proposed design is to place the dredged material to a target fill elevation of +3.0 feet which would ultimately settle to an approximate elevation of just under +0.75 feet NAVD88 (Geoid 12A) at TY20. Tidal creeks are expected to form naturally and containment dikes will be gapped and degraded to enhance the naturally formed tidal creeks.

Hydraulically dredged river sediments will be used to restore 10,625 linear feet of the Bayou Grande Cheniere Ridge. The ridge will have 25-ft crown width, a target height of +4.5 ft NAVD88, and side slopes of 1(V):8(H). Herbaceous plantings (e.g., seashore paspalum) will be necessary immediately after construction and bottomland hardwood species (seedlings and saplings) will be planted by Year 3. Funding for tallow control and maintenance plantings is also included.

In addition, 11,700 linear feet of earthen terraces will be constructed resulting in the creation of approximately 10 acres of wetlands benefiting 154 acres of open water. Each terrace segment will be approximately 450 feet long and built to an elevation of +3.0 feet, with a 25-foot crown width and 1(V):4(H) side slopes. The terraces will be constructed with a bucket dredge using in situ material from within the terrace field.

map

This project is located in Plaquemines Parish west of the Mississippi River near West Pointe a la Hache. Specifically, the project features are south of Lake Hermitage and along the eastern side of Bayou Grande Cheniere.

This project is on Priority Project List (PPL) 23.

The Bayou Grande Cheniere Marsh & Ridge Restoration project sponsors include:

Keep up with this project and other CWPPRA projects on the project page.

 

Freshwater Bayou Marsh Creation

banner-01

This area was damaged by Hurricanes Rita, Gustav, and Ike. Currently, Freshwater Bayou threatens to breach into the large interior open water and establish a hydrologic connection that previously did not exist. This would exacerbate the environmental problems affecting marshes in this area. Additionally, interior marsh loss has increased and organic soils are being exported into Freshwater Bayou. Interior marsh loss will increase without construction of the proposed project.

The project goals include: 1) creating/nourishing marsh and associated edge habitat for aquatic species through pipeline sediment delivery via dedicated dredging from the Gulf of Mexico or beneficial use of maintenance dredging from the Freshwater Bayou Canal; 2) restoring a wetland buffer between the large open water areas in the Mermentau Basin and Freshwater Bayou. Project features include creating and/or nourishing approximately 401 acres of marsh using dredge material.

map

The project features are located in Vermilion Parish, Louisiana in an area west of Freshwater Bayou and north of the Freshwater Bayou Locks.

This project is on Priority Project List (PPL) 19. 

The Freshwater Bayou Marsh Creation project sponsors include:

Keep up with this project and other CWPPRA projects on the project page.