Caminada Headlands Back Barrier Marsh Creation – Increment 2 (BA-193)

Dredged material from the Gulf of Mexico will be pumped into open-water areas which will create 250 acres of back barrier marsh and nourish 293 acres of emergent marsh behind 4 miles of the Caminada Beach.

Location

The Caminada Headland is defined as the area south of Louisiana Highway 1 between Belle Pass and Caminada Pass. The Project is located directly behind Caminada headland beach east of Bayou Moreau and west of Elmer’s Island. The Project is located in CWPPRA Planning Region 2, Barataria Basin, in Lafourche and Jefferson Parishes.

Problems

The Project is located in an especially dynamic area of the Louisiana Coast, experiencing some of the highest shoreline retreat rates in Louisiana averaging 41.4 feet/year over the last century.  Between 2006 and 2011 shoreline migration increased dramatically, exceeding 80 ft/yr near Bay Champagne and 110 ft/yr near Bayou Moreau. The increased losses occurred after Hurricanes Katrina and Rita in 2005 as the breaches remained open for an extended length of time which were then exacerbated by Tropical Storm Fay and Hurricanes Gustav and Ike in 2008. The prolonged breaches greatly increased the net export of sediment from the headland.

Restoration Strategy

The goals of this project are to: 1) Create and/or nourish 543 acres of emergent back barrier marsh, by pumping sediment from an offshore borrow site; 2) Create a platform upon which the beach and dune can migrate, reducing the likelihood of breaching, increasing the retention of overwashed sediment, improving the longevity of the barrier shoreline, and protecting wetlands and infrastructure to the north and west. The marsh creation and nourishment cells are designed to minimize impacts on existing marsh and mangroves.  Assuming some natural recruitment, vegetative plantings are planned for 50% of the project area, with half planted at TY3 and half at TY5 (if needed). Containment dikes will be degraded or gapped by TY3 for estuarine organism access. The project would result in approximately 160 net acres over the 20-year project life and would work synergistically with Caminada Headland Beach and Dune Restoration Projects (BA-45 and BA-143), as well as Caminada Headland Back Barrier Marsh Creation Project (BA-171).

BA193_20181109Progress to Date

The 30% design review and 95% design review meetings were held on July 10, 2018 and October 25, 2018, respectively. The Phase II Request for construction funding was presented to the CWPPRA Tech Committee on December 6, 2018.

This project is on Priority Project List 25.

The Federal Sponsor is EPA

The Local Sponsor is CPRA

Raccoon Island Shoreline Protection/Marsh Creation (TE-48)

wordpress fact sheet banner TE-48-01

The Isles Dernieres barrier island chain is experiencing some of the highest erosion rates of any coastal region in the world. Raccoon Island is experiencing shoreline retreat both gulfward and bayward, threatening one of the most productive wading bird nesting areas and shorebird habitats along the gulf coast.

An existing demonstration project on the eastern end of the island, Raccoon Island Breakwaters Demonstration project (TE-29), has proven that segmented breakwaters can significantly reduce, and perhaps even reverse, shoreline erosion rates. The primary goal of this project is to protect the Raccoon Island rookery and seabird colonies from the encroaching shoreline by: 1) reducing the rate of shoreline erosion along the western, gulfward side and 2) extending the longevity of northern backbay areas by creating 60 acres of intertidal wetlands that will serve as bird habitat.

This project has been separated into two construction phases, Phase A and Phase B. Phase A includes the construction of eight additional segmented breakwaters gulfward of the island and immediately west of the existing breakwaters demonstration project and an eastern groin that will connect existing Breakwater No. 0 to the island. Phase B involves the construction of a retention dike along the northern shore to create a back bay enclosure that will be filled with sediments dredged from the bay and/or gulf, followed by vegetative plantings.

map.jpg

The project is located in the Terrebonne Basin on the western-most island of the Isles Dernieres barrier island chain in Terrebonne Parish, Louisiana.

Rock breakwater construction for the prior demonstration phase of this project was completed on the east end of the island in June 1997. Sand deposits or “tombolos” have developed behind the breakwaters that protect and enhance the island. A less dramatic, however still positive effect, is expected to occur behind the 8 additional breakwaters being constructed to the west of the existing breakwaters.

Construction of Phase A was completed in September 2007 and Phase B in June 2013. All plantings are to be completed by the end of 2017.

This project is on Priority Project List 11.

The Federal Sponsor is USDA NRCS

The Local Sponsor is CPRA

Dustpan Maintenance Dredging Operations for Marsh Creation in the Mississippi River Delta Demonstration (MR-10)

wordpress fact sheet banner MR-10-01

Hopper dredges must dispose of their material in deep
water, making the spoil material unavailable for direct
marsh creation, although the material may still provide
nourishment for the system. In comparison to hopper
dredges, spoil from dustpan and cutterhead dredges can be
disposed of in shallow, open waters for marsh creation.

The project demonstrated the safe operation of a dustpan
hydraulic dredge in the critical Head of Passes reach of the
Mississippi River. This demonstration enables the use of
this type of dredge for the maintenance of this reach and
additional opportunity for the beneficial use of the dredge
material. Over the course of this demonstration project,
approximately 40 acres of deteriorated marsh that had
converted to shallow open water was restored with
approximately 222,000 cubic yards of dredge material
over the course of 8 days or 192 operating hours with the
expectation of an increase in marsh.

map.jpg

The project is located in Plaquemines Parish, Louisiana, in
the Mississippi River Modern Delta. Dredging took place
near Cubit’s Gap, Head of Passes, and Southwest Pass.

The demonstration was completed in June 2002.
This project is on Priority Project List 6.

Lake Hermitage Marsh Creation (BA-42)

wordpress fact sheet banner BA-42-01

The project is within the West Pointe a la Hache Mapping Unit which lost 38 percent of its marsh from 1932 to 1990. By the year 2050, 28 percent of the 1990 marsh acreage is expected to be lost. That loss is expected to occur even with operation of the West Pointe a la Hache Siphon (State project BA-04). Significant marsh loss has occurred south and east of Lake Hermitage and along the eastern lake shoreline. Deterioration of the lake rim has exposed interior marshes to the wave energy of Lake Hermitage and increased tidal exchange. Based on USGS land-water data from 1985 and 2006, the project area has an annual loss rate of -1.64%.

The original project features included dredging in the Mississippi River and pumping sediments via pipeline to create 549 acres of marsh. Additionally, 6,300 feet of shoreline restoration using river material and 7,300 linear feet of terraces were included. Fortunately, a favorable bid on the construction contract allowed for project expansion and the marsh creation feature was increased to encompass a total of 795 acres.

Funding from the Louisiana Oil Spill Coordinator’s Office, the Louisiana Department of Natural Resources – Office of Coastal Management, and Deepwater Horizon Early Restoration allowed construction of an additional 215 acres of marsh. Terraces were removed from the CWPPRA project to provide an area for marsh creation with Deepwater Horizon Early Restoration funding.

map

The project area is located in the Barataria Basin, south and east of Lake Hermitage in Plaquemines Parish, Louisiana near the community of West Pointe a la Hache.

The Louisiana Coastal Wetlands Conservation and Restoration Task Force approved funding for engineering and design in February 2006 and approved construction funding in January 2009. Construction began in February 2012 and was completed in June 2015.

This project is on Priority Project List 15.

The Federal Sponsor is USFWS

The Local Sponsor CPRA

Goose Point/Point Platte Marsh Creation (PO-33)

Interior ponding and, to a lesser extent, shoreline erosion are the major causes of wetland loss in the project area. Loss rates were highest during the period from 1956 to
1978. Those high loss rates were associated with hydrologic alterations which allowed salt water to penetrate the fresher marshes. During the transition to a more brackish plant community, large ponds were formed. A narrow strip of land separates those ponds from Lake Pontchartrain. Although the shoreline erosion rates are relatively low, the shoreline is already breached in several areas, and marsh loss in the interior ponds is expected to increase if the shoreline fails.

The goal of this project is to re-create marsh habitat in the open water behind the shoreline. This new marsh will maintain the lake-rim function along this section of the north shore of Lake Pontchartrain by preventing the formation of breaches into interior ponds. Sediment will be dredged from Lake Pontchartrain and contained in cells within the interior ponds to create approximately 417 acres of marsh. In addition, 149 acres of degraded marsh will be nourished with dredged material. Marsh will be created to widen the shoreline so that the ponds will not be breached during the course of normal shoreline retreat.

map.jpg

The project is located on the north shore of Lake Pontchartrain between Fontainebleau State Park and Louisiana Highway 11 and within the Big Branch Marsh National Wildlife Refuge in St. Tammany Parish, Louisiana. The project area at Goose Point also includes a portion of the St. Tammany State Wildlife Refuge.

On February 12, 2009, a final inspection of the project site was conducted. All construction activities are complete. This project is on Priority Project List 13.

 

The Federal Sponsor is USFWS

The Local Sponsor is CPRA

Little Lake Shoreline Protection/Dedicated Dredging Near Round Lake (BA-37)

wordpress fact sheet banner BA-37-01.png

The Little Lake mapping unit has high wetland loss caused by shoreline erosion, subsidence, and channel construction. The project is located in an area protecting approximately 3,000 acres of fragile interior marshes between the Little Lake shoreline and Bayou L’Ours Ridge. Project area wetlands are subject to high shoreline erosion rates (20 to 40 feet per year) and subsidence deteriorating interior marshes. Without construction, the project area marsh was expected to convert to mainly open water over the next 20 years.

The project’s goals were to:
1) prevent erosion along roughly 4 miles of Little Lake shoreline;
2) create 488 acres of intertidal wetlands along the Little Lake shoreline;
3) nourish and maintain 532 acres of intermediate marsh; and
4) reduce land loss rates by 50 percent over the 20-year life of the project.

The project consists of two major features, a shoreline protection structure and a marsh creation and nourishment area. The 25,976 ft foreshore rock dike was constructed by placing rocks on top of a geotextile foundation. The dike was constructed using three lifts and include gaps every 1,000 to 1,500 ft for fisheries access.

The marsh creation and nourishment phase of this project consisted of containment dikes, marsh creation in open water areas, and marsh nourishment over existing marsh. Approximately, 920 acres of marsh were created and nourished through placement of 3,165,121 cubic yards of sediment from Little Lake. The marsh creation area was planted with 17,000 Spartina alterniflora (smooth cordgrass) plugs.map.jpg

The project is located in the central Barataria Basin in Lafourche Parish, Louisiana. The project area is bounded by the East and West Forks of Bayou L’Ours and the southern shoreline of Little Lake from Plum Point westward to Breton Canal.

This project was selected for Phase I (engineering and design) funding at the January 2002 Task Force meeting and for Phase II (construction) funding in November 2003. Construction was completed in 2007.

The project is listed on Priority Project List 11.

Raccoon Island Shoreline Protection/ Marsh Creation (TE-48)

wordpress fact sheet banner TE-48-01

The Isles Dernieres barrier island chain is experiencing some of the highest erosion rates of any coastal region in the world. Raccoon Island is experiencing shoreline retreat both gulfward and bayward, threatening one of the most productive wading bird nesting areas and shorebird habitats along the gulf coast.

An existing demonstration project on the eastern end of the island, Raccoon Island Breakwaters Demonstration project (TE-29), has proven that segmented breakwaters can significantly reduce, and perhaps even reverse, shoreline erosion rates. The primary goal of this project is to protect the Raccoon Island rookery and seabird colonies from the encroaching shoreline by: 1) reducing the rate of shoreline erosion along the western, gulfward side and 2) extending the longevity of northern backbay areas by creating 60 acres of intertidal wetlands that will serve as bird habitat. This project has been separated into two construction phases, Phase A and Phase B. Phase A includes the construction of eight additional segmented breakwaters gulfward of the island and immediately west of the existing breakwaters demonstration project and an eastern groin that will connect existing Breakwater No. 0 to the island. Phase B involves the construction of a retention dike along the northern shore to create a back bay enclosure that will be filled with sediments dredged from the bay and/or gulf, followed by vegetative plantings.

map.jpg

The project is located in the Terrebonne Basin on the western-most island of the Isles Dernieres barrier island chain in Terrebonne Parish, Louisiana.

This project was selected for engineering and design funding at the January 2002 Breaux Act Task Force meeting. Construction funding for Phase A was approved in October 2004. Request for Phase B construction funding is anticipated to occur in January 2008.

This project is on Priority Project List 11.

The Sponsors include:

Federal Sponsor: NRCS

Local Sponsor: CPRA

Bayou Cane Marsh Creation (PO-181)

Po181_banner

Problems:
In 2005, the marshes in the North Shore Mapping Unit sustained severe damage due to Hurricane Katrina. Hundreds of acres of emergent marsh within this mapping unit were lost, resulting in hundreds of acres of shallow open water and scour ponds averaging about 2 ft deep. USGS calculated a 1984 to 2016 area loss rate of -0.91 % per year. Currently there is one area along the shoreline that looks as if a breach is forming. This area also has a small pond immediately behind the critical shoreline. If there were a breach in this area it would allow direct connection between the fresher interior marshes and higher salinity waters of Lake Pontchartrain.
Restoration Strategy:
The overall goal of this project is to restore marshes that were lost and/or damaged due to the effects of Hurricane Katrina. Restoring the marshes should reduce salinity effects on interior emergent marshes.
The proposed features of this project consist of filling approximately 384 acres of shallow open water and nourishing an additional 65 acres of fragmented and/or low marsh with material hydraulically dredged from Lake Pontchartrain. Target settled marsh elevation would be +1.2 NAVD 88, but will ultimately correspond to surrounding healthy marsh.
po_181_map
Progress to Date:
This project was approved for Phase I Engineering and Design on February 9th, 2018.
This project is on Priority Project List (PPL) 27.
Po181_sponsors

Goose Point/Point Platte Marsh Creation (PO-33)

wordpress fact sheet banner PO-33-01

Interior ponding and, to a lesser extent, shoreline erosion are the major causes of wetland loss in the project area. Loss rates were highest during the period from 1956 to 1978. Those high loss rates were associated with hydrologic alterations which allowed salt water to penetrate the fresher marshes. During the transition to a more brackish plant community, large ponds were formed. A narrow strip of land separates those ponds from Lake Pontchartrain. Although the shoreline erosion rates are relatively low, the shoreline is already breached in several areas, and marsh loss in the interior ponds is expected to increase if the shoreline fails.

The goal of this project is to re-create marsh habitat in the open water behind the shoreline. This new marsh will maintain the lake-rim function along this section of the north shore of Lake Pontchartrain by preventing the formation of breaches into interior ponds.

Sediment will be dredged from Lake Pontchartrain and contained in cells within the interior ponds to create approximately 417 acres of marsh. In addition, 149 acres of degraded marsh will be nourished with dredged material. Marsh will be created to widen the shoreline so that the ponds will not be breached during the course of normal shoreline retreat.

map

The project is located on the north shore of Lake Pontchartrain between Fountainebleu State Park and Louisiana Highway 11 and within the Big Branch Marsh National Wildlife Refuge in St. Tammany Parish, Louisiana. The project area at Goose Point also includes a portion of the St. Tammany State Wildlife Refuge.

On February 12, 2009, a final inspection of the project site was conducted. All construction activities are complete.

This project is on Priority Project List 13.

 

Federal Sponsor: USFWS

Local Sponsor: CPRA

West Belle Pass Barrier Headland Restoration (TE-52)

wordpress fact sheet banner TE-52-01.pngThis headland experiences some of the highest shoreline retreat rates in the nation, measuring over 100 feet a year in some locations. As the gulf encroaches upon the shoreline, sand is removed and the headland erodes. What was once a continuous shoreline spanning several miles has been reduced to less than half its original length. Furthermore, Hurricanes Katrina and Rita removed most of the emergent headland and dunes west of the pass. This headland helps provide protection to interior marshes and the Port Fourchon area; however, its continued degradation threatens the fragile bay habitat and infrastructure it once protected.

This project will reestablish the West Belle headland by rebuilding a large portion of the beach, dune, and back barrier marsh that once existed. Approximately 9,800 feet of beach and dune will be rebuilt using nearly 2.8 million cubic yards of dredged sand, and 150 acres of marsh habitat will be rebuilt using nearly 1.4 million cubic yards of dredged material. Native vegetation will be planted upon construction to help stabilize the rebuilt marsh and dune habitat.

map.jpg

The project is located along the Chenier Caminada headland to the west of West Belle Pass, at the southeastern edge of Timbalier Bay in Lafourche Parish, Lousiana.

This project was approved for engineering and design in October 2006. Construction funds were approved by the Task Force in late 2009, construction began fall 2011, and construction was completed in October 2012.

This project is on Priority Project List 16.

Federal Sponsor: NOAA NMFS

Local Sponsor: CPRA