GIWW (Gulf Intracoastal Waterway) to Clovelly Hydrologic Restoration (BA-02)

The constructed rock breakwater located in Bay L’Ours will assist in reducing wave energies before they impact the shore and will also arouse the curiosity of local waterfowl such as these pelicans.

Location

The center of the project area is in Lafourche Parish, Louisiana, approximately 5 miles southeast of Cut Off. It is bordered to the north by a pipeline canal north of the Clovelly Canal, to the west by West Fork Bayou L’Ours, to the east by Little Lake, and to the south by oilfield canals. The project encompasses 14,948 acres of primarily intermediate (94%) and brackish (6%) marshes.

Problems

The wetlands in the project area are of great importance to the ecological future of the Barataria estuary and to the protection of adjacent developed areas. The area is losing approximately 450 acres per year due to channelization, shoreline erosion, and saltwater intrusion.

Restoration Strategy

The project features include three rock weirs and four canal plugs. There is also a plug with a flap-gated culvert and one with a variable crest weir. In addition, there is a weir with a barge bay in the Clovelly Canal, 5,000 feet of shoreline reestablishment along project-area canals, and 6,000 feet of lake-rim reestablishment at Bay L’Ours. Finally, the spoil and marsh banks along canals in the project area’s southern perimeter are being maintained.

map

 

Progress to Date

The project was divided into two contracts in order to expedite implementation. The first contract was to install most of the weir structures. The second contract was to install bank protection, one weir, and one plug. The construction of the project’s unit 1 was completed in November 1997. Unit 2 was completed in October 2000.The O&M plan was signed in 2002. This project is on Priority Project List 1.

winch

This winch which is permanently attached to the variable crest, water control structure located right off Briton Canal, will help to configure the structure according to a pre-determined water management plan.

The project is on Priority Project List (PPL) 1.

The Federal Sponsor is Natural Resources Conservation Service.

The Local Sponsor is CPRA.

Approved Date: 1991
Project Area: 14,948 acres
Approved Funds: $12.7 M
Total Est. Cost: $12.8 M
Net Benefit After 20 Years: 175 acres
Status: Completed October 2000
Project Type: Demonstration: Hydrologic Restoration

GIWW – Perry Ridge West Bank Stabilization (CS-30)

Settlement plates such as the one pictured here will be used to determine if settling of the structure has occurred. Technicians from NRCS’s Crowley Watershed Office are shown taking baseline elevations before more rock is deposited. Future elevation readings will be taken after the structure is completed.

Location

The project is located along the northern bank of the Gulf Intracoastal Waterway (GIWW) between Perry Ridge and the Sabine River in Calcasieu Parish, Louisiana.

Problems

This section of the GIWW was dredged to allow the use of doublewide barges, and,  consequently, has intensified the occurrence of wake erosion. In addition, the construction of the Calcasieu Ship Channel and the deepening of Sabine Pass have increased the salinity and water currents within the GIWW. These activities have caused the GIWW shoreline to breach, thus impacting the interior marsh of the project area.

Restoration Strategy

Proposed project components involve installation of 9,500 feet of rock riprap along the northern bank of the GIWW from Perry Ridge to its intersection with the Sabine River.
An additional 2,200 feet of rock riprap will be installed from the Sabine/GIWW intersection north along the Sabine River. This proposed work is referred to as “construction unit number 2.” Approximately 22,952 linear feet of terraces will
be constructed in the shallow, open water areas north of the GIWW to reduce fetch (distance a wave can travel) and allow recovery of the interior marshes. Terraces will be
vegetated with 9,400 trade-gallon-sized plantings of California bulrush. This proposed work is referred to as “construction unit number 3.”

map

Progress to Date

Project construction is complete. The monitoring plan is currently in development and should be finalized in the spring of 2002.

The project is on Priority Project List (PPL) 9.

The Federal Sponsor is Natural Resources Conservation Service.

The Local Sponsor is CPRA.

Approved Date: 2000
Project Area: 1,132 acres
Approved Funds: $2.19 M
Total Est. Cost: $2.20 M
Net Benefit After 20 Years: 83 acres
Status: Completed
Project Type: Shoreline Protection

Atchafalaya Sediment Delivery (AT-02)

A bucket dredge is shown removing sediment from a shoaled-in channel in order to help reestablish water and sediment flow within the Atchafalaya Delta.

Location

The project is located east of the lower Atchafalaya River navigation channel in the Atchafalaya River Delta, approximately 19 miles southwest of Morgan City, Louisiana, in St. Mary Parish.

Problems

Growth of the lower Atchafalaya Delta has been reduced as a result of maintenance of the Atchafalaya River navigation channel. Delta development in the shallow waters of Atchafalaya Bay is dependent on distributary flows and the diversion of sediments into over-bank areas through crevasse channels.

Because of the placement of material dredged from the navigation channel and sediment accumulation within the channels that decrease flow efficiency, the open crevasse channels are frequently short-lived. As riverflow through a crevasse channel is reduced, the amount of sediment that can be deposited in the delta is likewise reduced, resulting in decreased marsh development.

Restoration Strategy

The purpose of this project is to promote natural delta development by reopening two silted-in channels and using those dredged sediments to create new wetlands. Approximately 720,000 cubic yards of sediment were dredged from Natal Channel and Castille Pass in 1998. Over 12,000 feet of channel were reopened, and more than 280 acres of new habitat were created by the strategic placement of the dredged channels’ sediments. By reestablishing water and sediment flow into the eastern part of the Atchafalaya Delta, an additional 1,200 acres of new habitat are expected to be naturally created over the life of the project.

map

Progress to Date

Construction was completed in 1998. A pre- versus post-construction habitat analysis using aerial photography indicated that, while there was an increase in land of 78.4 acres, the majority of the habitat created was represented by forested wetland (50.1 acres), while fresh marsh and upland barren habitats accounted for 14 acres gain each. Although many of the dominant plant species are present in both created and reference areas, the created areas contained different plant communities when compared to any time period in the development of a natural crevasse splay that served as a reference area for this project. Although the long-term effects on submerged aquatic vegetation (SAV) are unclear, habitat mapping indicated an increase in SAV habitat of 221.5 acres from 1997 to 1998, but this is very close to the increases that were reported in the project area pre-construction. Satellite imagery indicates that there have been significant increases in emergent acreage from 1998 to 2008.

This project is on Priority Project List 2.

The Federal Sponsor is National Marine Fisheries Service.

The Local Sponsor is CPRA.

Nutria Harvest for Wetland Restoration Demonstration (LA-03a)

Louisiana’s growing nutria population is detrimental to the state’s coastal marshes as the animals consume wetland plants that hold the soil together.

Location

This project was located throughout the coastal zone of Louisiana.

Problems

The nutria is a non-native, fur-bearing species in the rodent family that was introduced to enhance the Louisiana fur industry. Since the decline of the fur industry, nutria populations have increased tremendously along the coast. Because nutria voraciously consume marsh plants that help anchor wetlands, this non-native nutria population is now having a significant negative impact on coastal marsh health.

Restoration Strategy

The goals of this demonstration project were to determine if nutria meat for human consumption could be promoted and determine if a meat processing system promotional program could be developed. Meeting these goals would have facilitated nutria harvest through an increased meat demand. The project called for Coastal Wetlands Planning, Protection and Restoration Act funding matching that of participating meat-processing plants in order to compensate trappers for the nutria they harvest. The project also included monitoring selected coastal marsh areas by the Louisiana Department of Wildlife and Fisheries (LDWF) to assess both nutria damage and recovery resulting from this project.

Other components of the project included nutria meat recipe development and publication, along with an advertising and marketing strategy focused on increasing the public demand for nutria meat. The project was implemented by the LDWF with oversight by the Louisiana Department of Natural Resources and the U.S. Fish and Wildlife Service.

map

Progress to Date

This demonstration project was approved by the Louisiana Coastal Wetlands Conservation and Restoration Task Force in April 1997. Through this project, LDWF has coordinated with consultants to develop and implement various nutria meat marketing activities.

Marketing activities included LDWF staff activities and contracting with consultants to: (1) develop and evaluate local, national, and international nutria meat market potential for human consumption; (2) develop a nutria meat marketing plan, including a Nutria Marketing Strategic Report which proposed various ways to encourage the public to eat nutria; (3) participate in festivals and chef’s competitions; (4) distribute nutria meat to the public through sales at grocery stores, restaurants, and other retail outlets; (5) determine nutria meat processing costs, product price structure, and potential meat production volume; and (6) plan promotional and advertising activities based on the Nutria Marketing Strategic Report.

The LDWF 1999, 2000, and 2001 nutria coastal damage surveys and reports indicated continued nutria-related marsh damages in the Louisiana deltaic plain at a level of approximately 100,000 acres per year impacted. Because of the January 2002 Task Force approval of the larger Coastwide Nutria Control Program (LA-03b), the LDWF discontinued providing incentive payments to trappers and conducting nutria herbivory surveys under this demonstration project. Those two items will be funded under the larger project. However, funding for nutria meat processors enrolled in the program, as well as nutria meat marketing activities, continued until the project was completed in October 2003. This project is on Priority Project List 6.

The project is on Priority Project List (PPL) 6.

The Federal Sponsor is US Fish & Wildlife Service.

The Local Sponsor is CPRA.

Approved Date: 1997
Project Area: N/A
Approved Funds: $0.80 M
Total Est. Cost: $0.80 M
Net Benefit After 20 Years: N/A
Status: Completed
Project Type: Demonstration: Herbivory Control

East Catfish Lake Marsh Creation and Shoreline Protection (TE-157)

Aerial view of marsh creation project in Terrebonne Parish.

Location

The project is located in Region 3, Terrebonne Basin, Terrebonne Parish.

Problems

Significant marsh loss has occurred east and south of Catfish Lake. Causes of marsh loss include the construction of numerous oil/gas canals, subsidence, and sediment deprivation. Between Catfish Lake and Golden Meadow Hurricane Protection Levee, very little marsh remains after the construction of an extensive network of oil/gas canals. Much of the remaining land in this area consists of spoil banks and isolated patches of marsh. From examination of aerial photography, the majority of this loss occurred during the 1960s and 1970s. Based on the hypertemporal analysis conducted by USGS for the extended project boundary, the land loss rate in the project area is -0.86% per year for the period 1984 to 2019. Shoreline erosion rates (1998-2017) range from 10 ft/yr along the eastern lake shoreline to 22ft/yr along the southern lake shoreline.

Restoration Strategy

The primary goal of this project are; 1) restore marsh habitat in the open water areas east and south of Catfish Lake, and 2) restore and protect the eastern and southern Catfish Lake shoreline. The specific goals of this project are; 1) create 235 acres of marsh, 2) nourish 71 acres of marsh, 3) protect the marsh creation cells from shoreline erosion.

Service goals include restoration/protection of habitat for threatened and endangered species and other at-risk species. This project would restore habitat potentially utilized by the black rail, which is proposed for listing as a threatened species. The project could also benefit other species of concern including the saltmarsh topminnow and seaside sparrow.

Sediment from Catfish Lake will be hydraulically dredged and pumped via pipeline to create/nourish 306 acres of marsh. Dewatering and compaction of dredged sediments should produce elevations conducive to the establishment of emergent marsh and within the intertidal range. Containment dikes will be constructed around each marsh creation cell. Where practicable, material will be borrowed from perimeter oil/gas canals. Containment dikes will be gapped at the end of construction or by TY3. Approximately 2,566 linear feet of sheet pile wall will also be installed as a containment feature. Approximately 12,479 linear feet of shoreline protection (gabion mattresses) will be installed along the lakeside boundary of the marsh creation cells on the constructed containment dikes.

TE157_20200213

The project was approved for Phase I Engineering and Design in January 2020.

The project is on Priority Project List (PPL) 29.

The Federal Sponsor is US Fish & Wildlife Service.

The Local Sponsor is CPRA.

Bay Raccourci Marsh Creation and Ridge Restoration (TE-156)

Post project degraded marsh and open water.

Location

The project is located in Region 3, Terrebonne Basin, Terrebonne Parish.

Problems

High saline waters from Lake Mechant have directly contributed to the loss and/or conversion of much of the historically intermediate marshes to low salinity brackish marshes north of Lake Mechant. Subsidence, canal dredging and storm damage have also contributed significantly to the loss of marsh in the area. The zone of intermediate marsh (transition zone between fresh and brackish marshes) is located just north of Lake Merchant. High salinity water entering Bay Raccourci via Bayou Raccourci/Lake Mechant flows unimpeded into low salinity marshes surrounding Bayou Raccourci, effectively short circuiting the TE-44 Project. The 1984 to 2016 USGS loss rate is -0.32%/yr for the extended boundary area.

Restoration Strategy

The primary goals of this project are; 1) restore marsh habitat in the open water and degraded marsh areas via marsh creation and 2) restore forested ridge habitat along Bayou Decade.

The project would consist of the creation of 341 acres if marsh and 103 acres of marsh nourishment with sediments dredged from Lake Mechant and confined with earthen dikes. The proposed design is to place the dredged material to a fill height of +1.17 ft NAVD88. Dewatering and compaction of dredged sediment should produce elevations conducive to the establishment of emergent marsh and within the intertidal range. Containment dikes will be gapped at the end of construction.

The northern containment dike would be built to a height of +4.0 feet NAVD88 with a 10 feet wide crown and would also serve as a ridge. Material for the ridge would be bucket dredged from both Bayou de Cade and from within the marsh creation cell. The entire 16,350 linear feet (17 acres) of ridge would be planted with saplings and bare root seedlings on the crown and smooth cordgrass along the bayou side slopes.

The project would result in approximately 342 net acres over the 20-year project life.

TE156_20200213

The project was approved for Phase I Engineering and Design in January 2020.

The project is on Priority Project List (PPL) 29.

The Federal Sponsor is US Fish & Wildlife Service.

The Local Sponsor is CPRA.

Phoenix Marsh Creation – East Increment (BS-42)

Degraded marsh in coastal Louisiana.

Location

The project is located in Region 2, Breton Basin, Plaquemines Parish.

Problems

Two major causes of wetland loss for this area are sediment deprivation and saltwater intrusion. Altered hydrology and oil/gas development have exacerbated this loss. Much of the fresh and intermediate marsh that once existed earlier in this century has either converted to more saline habitats or has become open water as a result of oil/gas canals, subsidence, and a lack of sediment deposition. The 1984 to 2019 USGS land change rate is -0.78% per year.

Restoration Strategy

The project goal is to restore 392 acres of marsh in the open water areas between Bayou la Croix and River aux Chênes through the placement of dredged material via hydraulic dredging. This project will work syngeristically with projects to the east by creating continuity with the Breton Landbridge Marsh Creation (West) Project (BS-38) and the Mid Breton Landbridge Marsh Creation and Terracing Project (BS-32). This proposed first increment would extend the reach of the Breton Landbridge and is part of an overall, long-range, restoration goal to create/nourish 1,000 to 2,000 acres of intermediate marsh across 5 miles of the Breton Sound Basin from River aux Chênes to the Mississippi River.

Sediment will be hydraulically dredged from the Mississippi River. The dredged riverine sediments will be pumped via pipeline into two semi-confined disposal areas. Where feasible, existing marsh will be used as containment instead of containment dikes.

Vegetative plantings are not proposed in the marsh creation areas, and containment dikes will be gapped no later than year three post construction.

Service goals include restoration/protection of habitat for threatened and endangered species and other at-risk species. This project would restore habitat potentially utilized by the black rail, which is proposed for listing as a threatened species. The project could also benefit other species of concern including the saltmarsh topminnow and seaside sparrow.

BS42_20200213

The project was approved for Phase I Engineering and Design in January 2020.

The project is on Priority Project List (PPL) 29.

The Federal Sponsor is US Fish & Wildlife Service.

The Local Sponsor is CPRA.

North Delacroix Marsh Creation and Terracing (BS-41)

NOAA staff gather data to inform project design. 

Location

The project is located in Region 2, Breton Basin, St. Bernard Parish.

Problems

Hurricanes Katrina and Rita caused the majority of wetland loss in the project site. Wind erosion and saltwater intrusion have resulted in loss of marsh vegetation and wetland soils. Marsh loss has increased exposure of Delacroix to flooding from the east/ southeast. The 1984 to 2019 USGS loss rate is -1.4%/ year for the extended project boundary area.

Restoration Strategy

The project goal is to create and nourish approximately 389 acres of marsh and construct approximately 8,548 linear feet of terraces utilizing a layout to help protect the community of Delacroix.

Sediment would be hydraulically dredged from Lake Lery and placed into two confined disposal areas creating 322 acres of marsh and nourishing 67 acres of existing marsh. Two creation cells allow a channel for drainage. Approximately 8,548 ft of earthen terraces would be constructed. The terraces would be strategically placed east of the northern marsh creation cell and south of the southern cell. Dewatering of the marsh creation cells into areas adjacent to the terraces would take advantage of sediment laden water trapping the particulates to create additional marsh. Terraces would be planted with appropriate bare root plants 2.5 ft apart in one row per side and crown. Created marsh will not be planted.

Containment dikes will be gapped no later than three years after construction. Two additional areas of deteriorating marsh south and east of the proposed project will be investigated. Data acquisition for engineering and design would include an additional
349 acres to allow robustness for these additive or alternate features during Phase I.

BS-41_ProjectMap_Feb2020

The project was approved for Phase I Engineering and Design in January 2020.

This project is listed on Priority Project List 29.

The Federal Sponsor is NOAA NMFS.

The Local Sponsor is CPRA.

A Coastal Visit From St. Nicholas

Please enjoy this CWPPRA Parody of Moore’s holiday classic “A Visit From St. Nicholas,” more widely recognized as “The Night Before Christmas.”

 

‘Tis the day we call Christmas and all through the marsh,

The conditions are getting unusually harsh.

Their flowers are wilting, the shrubs getting bare

In response to the cold and dry air that is there.

 

Losing some green as the maples turn red,

Creatures prepare for hard times just ahead.

Drakes coming south, [1] with their females so drab,

Their sexes dimorphic, just like a blue crab.

 

Unlike the crab, though, get out of the water;

The crabs get to rest until it gets hotter.

They bury themselves in the mud and the mash, [2]

Unfortunate ones have to bury in trash! (Please don’t litter.)

 

Our coast doesn’t freeze much but this year might go

To 32 Fahrenheit, maybe below.

Some creatures go far, but some must stay near,

Plants and their roots are anchored right here.

 

Cold can be dangerous, plants can get sick,

Mangroves don’t have a cold-weather trick.

They deal with the salt and they deal with the rain,

But mangroves fear cold, so South they remain. [3]

 

The Turtles, the gators, the lizards, the snakes,

All have cold blood, and so they brumate. [4]

So, hang all your wreaths and deck all the halls,

But think of the wildlife, no matter how small.

 

Habitat loss can hurt plants just as well,

Even those plants that are one simple cell.

Some plants can float and some plants can grow stalks;

yet to be found is a plant that can walk.

 

But wait! We humans have legs we can use

To move plants to places, like in Calcasieu.

Pontchartrain, Breton Sound, Atchafalaya,

These wetland basins now cook jambalaya.

 

We love our heritage and love spicy food;

we also love science that’s been peer-reviewed.

The Delta gets sediment and it slowly grows,

But what of the rest that sits under our nose?

 

Let’s restore our coast, let’s give it a try,

Think about those who can swim, walk, or fly.

Those who are sessile, of course, matter too.

CWPPRA loves wetlands, alive through and through.

 

Our work is important, it always gets better,

sometimes with projects that work well together.

Funding the coastline is not just a show,

It helps our plants and our wildlife grow.

 

Other good things that come from restoring

Are seafood, and commerce, and outdoor exploring.

We protect ports and some habitat too,

We protect cities and we protect you.

 

Enough of the bragging, there’s still more to learn

On techniques we use to reduce the concern!

We nourish beaches to give seabirds refuge

And rebuild salt marsh for protection from deluge.

 

Working away, we burn midnight’s oil

To stop salt intrusion and relocate soils.

We plan with our partners to restore the most

For CWPPRA to work on Protecting Our Coast.

 

[1] https://www.birdwatchersdigest.com/bwdsite/explore/regions/southeast/louisiana/louisiana-birding-season-fall.php

[2] https://www.bluecrab.info/faq.htm

[3] https://databasin.org/datasets/6ec804f5250a483abd9bdb200939247f

[4] http://www.loyno.edu/lucec/natural-history-writings/where-do-alligators-go-winter

Featured image from http://www.realestnature.com/south-louisiana-salt-marsh-fishing/

Original poem:

Moore, C. (1823). A Visit from St. Nicholas (‘Twas the Night Before Christmas). A Visit from St. Nicholas (‘Twas the Night Before Christmas)(Lit2Go Edition). Retrieved December 18, 2018, from http://etc.usf.edu/lit2go/234/a-visit-from-st-nicholas-twas-the-night-before-christmas/5903/a-visit-from-st-nicholas-twas-the-night-before-christmas/

 

South Lake De Cade Freshwater Introduction (TE-39)

wordpress fact sheet banner TE-39-01

The project area is experiencing marsh deterioration due to subsidence, rapid tidal exchange, and human-induced hydrologic changes that result in increased salinities. Saltwater intrusion has caused a shift in marsh type and a conversion of over 30 percent of emergent vegetation to open water habitat. Shoreline erosion along the south embankment of Lake De Cade threatens to breach the hydrologic barrier between the lake and interior marshes.

Proposed project components include installing three control structures along the south rim of the lake and enlarging Lapeyrouse Canal to allow the controlled diversion of Atchafalaya River water, nutrients, and sediments south into project area marshes. Outfall management structures are planned in the marsh interior to provide better distribution of river water. In addition, approximately 1.6 miles of foreshore rock dike is planned to protect the critical areas of the south lake shoreline from breaching.

map

The project is located in Terrebonne Parish, approximately 15 miles southwest of Houma, Louisiana.

After initial engineering investigation, the project was divided into two construction units. Construction unit one consisted of the shoreline protection only and was completed in July 2011. Construction unit two consisting of the freshwater introduction component was further investigated and due to uncertainty of benefits was not constructed, and therefore, the project is considered completed.

This project is on Priority Project List 9.

The Federal Sponsor is NRCS

The Local Sponsor is CPRA