The goal of building terraces is to achieve some of the same objectives as full marsh creation but over a larger area of open water, where marsh creation alone is not feasible. Terraces are long, earthen berms that are built by mechanically dredging material and piling and shaping the material to a desired height. Most terraces average around 3 feet tall, with shallow side slopes and a wide base. This size and shape optimize the amount of terrace that falls in the intertidal zone and will support wetland vegetation.

The objectives of constructing terraces are several and depend upon the location in which they are built. These include acting as a sediment trap to help build new land, reducing wave fetch and erosion on adjacent marsh shorelines, creating habitat for fish and waterfowl, and improving water quality to promote the growth of aquatic vegetation. Terracing projects constructed under CWPPRA have achieved each of these goals, with sediment trapping being most evident near the openings of sediment-laden bays or navigational waterways.

Terracing has become a widely used technique that is expanding across the Gulf Coast because of the success and cost-effectiveness demonstrated through CWPPRA and privately funded projects. Although these features may not look like natural marsh and often use geometric configurations, they are able to perform a lot of the functions of natural marsh in areas that have become vast open water. Developing this cost-effective technique for use in areas that have few other restoration options is a testament to CWPPRA’s ability to adapt to funding constraints and a quickly changing environment.

aerial
TV-12 Little Vermilion Bay Sediment Trapping

 

 

 

 

Bayou Grande Cheniere Marsh & Ridge Restoration

banner

Significant marsh loss has occurred south of Lake Hermitage with the construction of numerous oil and gas canals, subsidence, and sediment deprivation. The most significant loss occurred during the 1960s and 1970s. Based on the hyper-temporal analysis conducted by USGS for the extended boundary, loss rates in the project area are estimated to be -1.16% per ear for the period 1984 to 2011.

The goals of the Bayou Grande Cheniere Marsh and Ridge Restoration Project (BA-173) are to restore marsh habitat adjacent to the eastern shoreline of Bayou Grande Cheniere, reestablish the corresponding section of the bayou’s forested ridge habitat along this shoreline, and create terraces to restore marsh in open water habitat. Specific objectives are to 1) restore 302 acres of brackish marsh habitat, 2) construct the marsh platform to an elevation that supports healthy marsh; 3) reestablish 10,625 linear feet of the historic Bayou Grande Cheniere Ridge to an elevation that supports healthy woody vegetation, 4) establish the ridge with diverse native woody species, and 5) construct 12,000 linear feet of terraces to an elevation that will support healthy marsh.

Riverine sediments will be hydraulically dredged and pumped via pipeline to create/nourish approximately 302 acres of marsh. Containment dikes will be constructed around the perimeter of the marsh creation cells. The proposed design is to place the dredged material to a target fill elevation of +3.0 feet which would ultimately settle to an approximate elevation of just under +0.75 feet NAVD88 (Geoid 12A) at TY20. Tidal creeks are expected to form naturally and containment dikes will be gapped and degraded to enhance the naturally formed tidal creeks.

Hydraulically dredged river sediments will be used to restore 10,625 linear feet of the Bayou Grande Cheniere Ridge. The ridge will have 25-ft crown width, a target height of +4.5 ft NAVD88, and side slopes of 1(V):8(H). Herbaceous plantings (e.g., seashore paspalum) will be necessary immediately after construction and bottomland hardwood species (seedlings and saplings) will be planted by Year 3. Funding for tallow control and maintenance plantings is also included.

In addition, 11,700 linear feet of earthen terraces will be constructed resulting in the creation of approximately 10 acres of wetlands benefiting 154 acres of open water. Each terrace segment will be approximately 450 feet long and built to an elevation of +3.0 feet, with a 25-foot crown width and 1(V):4(H) side slopes. The terraces will be constructed with a bucket dredge using in situ material from within the terrace field.

map

This project is located in Plaquemines Parish west of the Mississippi River near West Pointe a la Hache. Specifically, the project features are south of Lake Hermitage and along the eastern side of Bayou Grande Cheniere.

This project is on Priority Project List (PPL) 23.

The Bayou Grande Cheniere Marsh & Ridge Restoration project sponsors include: